S.No Name of Work Estimated Amount Work Start Date DOC
Work Completed
Physical Work Done % Expenditure Rs. in lakhs %
Balance Work to be Done
Physical % Financial Amount Rs.in lakhs %
Actual Date of Completion Agency Name Remarks -----
APTDC Deposit work
 
1 Development of landscape from Spot NO. 15 to Spot No. 21 at R.K Beach to Park Hotel Jn. 36.82 16-11-2014 15-1-2015 Work completed in Spot No. 15 to 18. 36 6.08 16 soon aftercopmpletion of Civil works and laying of Pipe Line by APTDC 30.74 Remaining work held up for want of Civil works and laying of pipeline by APTDC M/s. Glad farom India Pvt. Ltd., and Reply from APTDC is awaited
INTERNATIONAL FLEET REVIEW
 
1 Kursura Submarine Museum, Development of Landscape Garden at Kursura Submarine Museum in view of IFR 6.3 15-09-15 30.11.15 0 0 0 0 M/s. Sri Seetha Rama Nursery Gardens & Sri. B. Palavelli Agreement concluded on 15.9.15.
NTPC Deposit work
 
1 Raising 5000 Nos avenue on Barren Hill in Survey No. 275 of Simhachalam Devasthanam land 22.83 29-1-2015 28-9-2015 Plantation Work completed. Mainteance operations continued. 100 19.41 85.01 3.42 05.04.15 M/s. Green Lawns Nursery Gardens Plantation Work completed. Mainteance operations continued.
VUDA CENTRAL PARK
 
1 Avenue plantation and edge plantation along the internal jogging track and Cycle track 8.78 01-05-2015 31-7-2015 Work completed 100 1.75 17.88 7.03 M/s. Green Lawns Nursery Gardens Work completed
2 Raising of Bamboo Plants at Bamboo Gardens 3.92 0 0 0 0 3rd Time Tenders invited
VUDA Nurseries
 
1 Raising of 65000 Nos bag plants for 4”x7”, 5”x9” and 8”x12” bag plants at MVP Central Nursery 3.62 25-4-2015 24-6-2015 Work completed 100 2.66 73.48 0.96 05.07.15 M/s. Kailash Jogging Track Gardeners Society Work completed