  BRIEF NOTES ON ENGINEERING WORKS

-----------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------

1) MASTER PLAN ROADS DEVELOPMENT–Rs.53.24 Cr.

(a) Completed Works Rs.37.50 Cr.
Sl.No Name of the Road Length of the road (In KM) Estimate Amount(Rs. In Lakhs)
1 100’0” wide road Boyapalem jn., at NH 16 to Kapuluppada village (4 lane BT surface) 2.80 459.00
2 Left over Beach road stretch near Zoo to Seethakonda Road 0.40 125.00
3 Payakaraopeta Road (2 lane BT surface) 1.60 190.00
4 100’0” wide road from Law College at NH-16 Jn. to Pebble Beach Housing (extra widening with footpaths & Greenery) 3.10 1219.00
5 80’0” wide road from R&B Guest house junction to Paul Nagar Junction via K.A.Peta, Vzm (4 lane BT surface) 1.30 322.00
6 100’0” wide Githam College road leftover stretch 0.40 85.00
7 100’0” wide road from Marikavalasa jn. to Beach road (strengthening & re-carpeting) 6.50 700.00
8 100’0” wide road from Anakapalli - Pudimadaka Road (strengthening & re-carpeting 2 lane BT surface) 13.00 650.00
(b) Master Plan Roads in progress - Rs.15.74 Cr.
Sl.No Name of the Road Length of the road (In KM) Estimate Amount(Rs. In Lakhs)
1 60’0” wide Sabbavaram to Gullepalli road 1st Phase BT surface 2 lane) 3.75 970.00
2 Road from RTC Bus station junction to Railway station (YelamanchiIi Railway station Road) 0.64 220.00
3 Left over odd Master Plan Road stretches (which are free from court disputes)
(a) Bakkannapalem 0.25 144.00
(b) Revallapalem 0.11 95.00
(c) Nagarampalem 0.80 145.00

2) Assets

  • Construction of convention center at Cheemalapalli of Pendurthi Mandal.
    G+1structure : 1000 Nos capacity
    Site Area : 4507.07 Sqm
    Built up area : 1756.06 Sqm (864 sqm GF + 892.06 sqm – FF)
    Total Project cost : Rs. 6.75 Crs
    Rs. 2.00 Crs. ( MP funds) + 4.75 Crs. VMRDA Funds
    Physical Progress and Status : RCC Frame work completed and Masonry work is in progress. Remaining work (completion by 11/2024)
  • Construction of Convention center at Yendada Village of Bheemili Mandal
    G+1structure : 1000 Nos capacity
    Site Area : 5362.27 Sqm
    Built up area : 1756.06 Sqm (864 sqm GF + 892.06 sqm – FF)
    Total Project cost : Rs.7.67 Crs
    Rs.2.00 Crs. (MP funds) + 5.67 Crs. VMRDA Funds.
    Physical Progress and Status : RCC Frame work completed and Masonry work is in progress. Remaining work (completion by 11/2024)
  • Multi-Level Car Parking Project at Siripuram Jn, Visakhapatnam
    Estimate project cost : Rs.87.50 Cr
    3 Basement floors + 2 Floors parking area : 1.90 Lakh sft
    Accommodation of vehicles :
    4 Wheelers : 430 Nos
    2 Wheelers : 400 Nos
    6 Floors Commercial space : 1.64 lakh sft
    Date of Completion : 31st August 2024
Status: Total frame work completed for 11 floors and interior works are in progress.

3) MIG SMART TOWNSHIP LAYOUTS :

Sl.No District Village Extent (Ac.) No. of plots Sale price per sq.yard. (Rs.) No. of plots allotted through e-lottery Estimated amount for development(Rs.in Cr.) Package -I Details (QR roads, CC Drains & CD works etc.,)(Rs.in Cr.) Present development status
1 Visakhapatnam Palavalasa–I& II 76.96 558 14,500 164 38.47 11.97 Quarry Rubbish Road completed and Drains work is in progress
2 Anakapalli Adduru 20.00 165 6,500 Nil 11.40 7.32 Quarry Rubbish Road completed and Drains work is in progress
3 Anakapalli Bhogapuram & Chodepalli 51.89 183 11,000 Nil 35.74 3.49 Jungle clearance and site levelling is in progress
4 Vizianagaram Raghumanda 22.50 287 6,500 177 11.23 3.82 CC Drains completed and CC road work is in progress
5 Vizianagaram Jiyyannavalasa 12.31 152 7,500 86 6.15 3.37 CC Drains completed and CC road work is in progress
6 Vizianagaram Garividi 21.30 272 7,700 Nil 12.15 8.00 CC Drains completed and CC road work is in progress
204.96 1617 115.14

4) Projects

  • Beach Deck: near VMRDA Park
    Estimate project cost : Rs.7.80 Cr.
    Salient features :
    1st Floor (Upper Deck) : 18Mts.x12Mts.(216 Sq.mtrs)
    Ground floor (Lower Deck) : 24Mts.x18Mts.(432 Sq.mtrs)
    Walk way : 45Mts. on Beach and 46 Mts on sea and width of 6 Mts.
    Commercial establishments : Shops, food stalls-18 Nos. (150Sft. Each stall), dining plaza, landscaping with parking facility are provided along the island at the entry plaza
    Status : Work entrusted to M/s.Vijay Nirman Company Pvt Ltd. Work will be commenced after the clearance of CRZ.
  • Adventurous Sports on Kailasagiri - “Design- Invest– Installation and operation” model for 3 years on pilot basis (PPP)
    1. Zip liner
    2. Sky cycling
    3. Glass Sky walk Bridge
    4. Revenues - 45% share on Gross Revenue.
    5. Status – Work is in progress.
  • Re-Development of Vysakhi Jala Udyanavanam as an Urban Entertainment Project
    1. Components are (i) Amusement & Fun Zone (ii) Drive-in & Parking and (iii) Multi-cuisine Food Zone etc.
    2. Extent Ac.3.48 Cts.
    3. Project cost Rs.40.00 Crs.
    4. Tenders to be invited
  • Development of Nature Cottages, Revolving Restaurant and Beach View Cafe at Kailasagiri
    1. Extent Ac.1.99 Cts.
    2. Project cost - Rs.18.00 Crs.
    3. Tenders to be invited
  • Development of Convention Centre with not less than 5 Star Hotel/ Resort ( in about) adjacent to VMRDA Park on Beach Road, Visakhapatnam
    1. Extent Ac.7.97 Cts
    2. Project cost Rs. 220 Crs.
    3. Tenders to be invited
  • Natural History Park & Museum-Research Institute at Visakhapatnam, estimate cost of Rs.88.00 Cr. (GoI: Rs.38 Cr. & VMRDA: Rs.50 Cr.) – DPR sent to Govt., of A.P for approval.
  • Construction of Science Museum by Science City of Andhra Pradesh. Project cost is Rs.4.69 Crs.(Rs.3,75,20,000/- from Ministry of Cultural, Government of India + Rs. 93,80,000/- from Government of AP. – 3D Art Gallery – Augmented Reality (AR) – Silica Statues – Solar Exhibits – Space Exhibits– (ISRO -Indoor & Out-Door-Exhibits)- Science working Models – 1st Slab work is in progress.
  • Railway over Bridge (ROB) at NAD Flyover
    Project Cost : Rs.28.00 Cr
    Present Status : Pile Foundation work is in progress
    Status : Work in progress - Completion by 31st December, 2024

5) One (1) Cent Plot Layouts

  • Total of 83 one cent Layouts were developed in an extent of Ac.4828.00 Cts (1,41,654 plots) and with an expenditure of Rs.175 Cr. including temporary infra like approach roads, bore wells with service connection, cement godowns
  • RC Plot layouts development under Land Pooling:
    1. VMRDA has taken up development of basic infrastructure facilities to Re-Constituted plot layouts with a project cost of Rs.660 Cr. in 3 phases.
    2. Phase-I: Sanctioned development so far for Rs.150 Crores which includes Quarry Rubbish roads, Storm water CC Drains & CD works. 60% of works are completed and remaining are in progress.
    3. Total revised area of Reconstituted layouts in 48 layouts– Ac.1215 Cts.
    4. Phase – II: Development works i.e., providing BT / CC Roads, Avenue Plantation and development of parks, Layout Electrification, administrative sanction accorded for Rs.305 Cr.
    5. Phase – III: Development works i.e., Water supply & UGD for Rs.155 Cr., yet to be taken.

6) Newly proposed PPP /EPC works

  • Visakhapatnam IT City Madhurawada, Visakhapatnam
    Project Cost : Rs.200 Cr
    Extent : Ac. 22.19 Cts
    Present Status : 1. Site survey, boundary marking & contour survey is completed with tentative layout.
    2. Site Master Planning to be finalized
  • Development of Urban Habitat Centre at Rushikonda
    Project Cost : Rs.500 Cr
    Extent : Ac. 7.00 Cts
    Present Status : Expression of Interest (EoI) to be invited for finalization of RFP
  • Development an Urban Entertainment Zone
    Project Cost : Rs.50 Cr
    Extent : Ac. 3.50 Cts
    Present Status : Expression of Interest (EoI) to be invited
  • Development of Outdoor Sports Arena at Madhurawada
    Project Cost : Rs.20 Cr
    Extent : Ac. 2.98 Cts
    Present Status : Site is having constructed with compound wall and fencing allround and ready to take up the project
  • Construction of Commercial Complex cum Office space behind VMRDA office at Siripuram Junction, Visakhapatnam
    Project Cost : Rs.60 Cr
    Extent : Ac. 0.70 Cts
    Present Status : Proposals / Mode of development to be finalized for taking up the project
  • Development of International Amusement Park and Entertainment Zone at Annavaram Village, Bheemunipatnam Mandal (Nearby Bhogapuram International Airport)
    Project Cost : Rs.150 Cr
    Extent : Ac. 40.00 Cts
    Present Status : Expression of Interest (EoI) to be invited.